• mn
IPO

Trade Reports

Index

51674.98

( -49.49 -0.1% )
Index Unit Change
Top 20 Index 51674.98 -49.49
MSE A Index 19943.91 -8.05
MSE B Index 15516.13 -1.29

News

B. DULGOON HAS BEEN APPOINTED AS THE ACTING EXECUTIVE DIRECTOR OF THE "MONGOLIAN STOCK EXCHANGE" JSC.

2025-01-17 17:44:36

By resolution No. 2 dated January 16, 2025 by the Board of Directors, J. Tsogtbayar has been relieved from his duties as the Acting Executive Director and B. Dulgoon has been appointed in his place.

JANUARY 17, TRADING REPORT

2025-01-17 16:26:15

Total trade: MNT 18,540,810,499 (USD 5,407,202.43) 

THE TOP 20 INDEX PORTFOLIO OF THE MONGOLIAN STOCK EXCHANGE HAS BEEN UPDATED

2025-01-16 18:00:18

"XacBank" JSC, "Premium Nexus" JSC, "Ard Financial Group" JSC, and "LendMN NBFI" JSC have been added to form the updated portfolio.

News

ATTENTION TO THE SHAREHOLDERS OF 'ERDENE RESOURCES DEVELOPMENT CORPORATION'

2019-02-11 11:01:58

Erdene Resource Development Corp. (TSX:ERD; MSE:ERDN) has announced the filing on SEDAR of the independent Preliminary Economic Assessment (PEA) Technical Report for its 100%-owned Khundii Gold Project in southwest Mongolia.

The PEA envisions a high-grade, open-pit mine, producing an average of 51,200 oz per year at an average grade of 3.42 g/t gold over eight years. The development incorporates a conventional gravity separation circuit and a carbon-in-pulp plant with processing capacity of 1,800 tonnes per day. The key Project metrics are highlighted below:
• After-tax NPV5% of US$99 million and IRR of 56% at a US$1,200/ oz gold price;
• After-tax NPV5% of US$124 million and IRR of 68% at a US$1,300/oz gold price, demonstrating significant leverage to gold prices;
• Low initial capital expenditure of US$32 million, using a contract mining fleet;
• All-in sustaining cash cost (“AISC”) of US$714/oz of recovered gold;
• Payback of less than 2 years. 

Please click here to view the full release. 